Writing Project Schedule

Writing Project Schedule

 

Project Schedule
Due Week 10 and worth 150 points

This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule
(Submit as one [1] Microsoft Project file)

  1. In Assignment 2, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule.
    Your project must include the following criteria:

    • The project must consist of at least twenty-five (25) tasks. 
    • Each task must contain a start date, a finish date, and have main staffing and non-staffing resources assigned. 
    • Assume that your work activities are completed during normal weekdays (no weekend work) under normal conditions (8 hours per day). 
    • In terms of holidays, you can assume no work will be done the following days: New Year’s Day, President’s Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year’s Eve.

Part B: Written Response
(Submit as a Microsoft Word file)

Write a one to two (1-2) page response in which you:

  1. Analyze your project in terms of project completion, critical path, and slack / float. Specifically, be sure to answer the following: 
    • When will the project be completed? 
    • What is the critical path for the project?
    • How much slack / float is in your project? What activities have the greatest slack / float?
  2. Summarize the recommendations or improvements you would make to your project schedule. Specifically, be sure to answer the following:
    • Identify the top three (3) activities that you believe could impact the project completion date.
    • What additional activities would you add to this project to make it more complete, from a project management viewpoint?
  3. Format your assignment according to the following formatting requirements:
    • Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.
    • Include a cover page containing the title of the assignment, the student’s name, the professor’s name, the course title, and the date. The cover page is not included in the required page length.

Details about the project

Ignoring the holidays, the project is 695 days long. It starts on Wednesday, 29th September 2017 and finishes on Tuesday 25th August 2020. All the tasks that are pertaining to the flow of work belong to the overall tasks that lie ahead. The critical path is highlighted below:

From the perspective it can be seen that there are two critical paths and in those paths only task 6 and 8 differ as they are parallel. So the critical paths are 14569131419 and 14589131419. All of these tasks are vital for the composition. It can therefore be told that these activities have no slack. All the activities with and without slack are given below

Task Name Finish Slack
Baseball Stadium 0 days
Clear Stadium Site 0 days
Demolish Building 210 days
Set up Construction Site 525 days
Drive Support Piling 0 days
Pour Lower Concrete Bowl 0 days
Pour Main concourse 0 days
Install Playing field 275 days
Construct Upper Steel Bowl 0 days
Install Seats 0 days
Build Luxury Boxes 155 days
Install jumbotron 235 days
Stadium Infrastructure 125 days
Construct Steel Canopy 0 days
Light Installation 0 days
Build Roof Supports 5 days
Construction Roof 5 days
Install Roof Tracks 95 days
Install Roof 5 days
Inspection 0 days

The top three activities are that have the largest slack, setting up construction site, installing playing field and installing jumbotron